Home

Malletts Bay Boat Club
Lake Champlain Founded 1936








==============================================================================================

Launch Mooring Puller

4/25/2015
Put mooring puller in the water & tie up to dock. Install engine

Day and TimeTaskSupport Personnel
Thursday 1400 - 1530 Puller in water, hang engine Jonathon Haas
Thursday 1400 - 1530 Puller in water,hang engine Zoltan Sachs
Thursday 1400 - 1530 Puller in water, hang engine Mark Anderson
Thursday 1400 - 1530 Puller in water, hang engine Dave Jillson

==============================================================================================

First Work of the year

5/2/2015
Replace barrel straps under mooring puller
Put mooring puller in water
Move to floating dock

Day and TimeTaskSupport Personnel
Saturday 0900 - 1100 Breaking Sticks Volunteer Needed
Saturday 1000-1100 Diver 2 Volunteer Needed
Saturday 1000-1100 Diver Volunteer Needed
Saturday 1000-1100 Diver Volunteer Needed
Saturday 1000-1100 Diver Volunteer Needed

==============================================================================================

Launch Harbor Whaler

5/7/2015

Day and TimeTaskSupport Personnel
Thursday 1530 - 1700 Surface 1 Denis Lambert
Thursday 1530 - 1700 Surface 2 Tom Peterson
Thursday 1530 - 1700 Surface 3 Jonathon Haas

==============================================================================================

Club Opening delete

5/9/2015
ARRIVE BY 0900 FOR A HARBOR COMMITTEE GROUP PHOTO!

Day and TimeTaskSupport Personnel
Saturday 0900 Clean Harbor Shed Jonathon Haas
Saturday 0900 - 1100 Diver Volunteer Needed
Saturday 1000-1100 Diver 1 Volunteer Needed

==============================================================================================

Testing Committee

5/10/2015
Testing Committee as a variable

Day and TimeTaskSupport Personnel
Saturday 1000-1100 Picking up sticks Volunteer Needed

==============================================================================================

Adding again

5/11/2015
a href=EditSchedule.asp?choice=5&ID

Day and TimeTaskSupport Personnel
Saturday 1000-1100 Putting Sticks back Volunteer Needed

==============================================================================================

Continue mooring inspections

6/27/2015
31 Moorings inspected

Day and TimeTaskSupport Personnel
Saturday 0800 - 1300 Diver 1 Gerald Couture
Saturday 0800 - 1300 Diver 2 Bradley Feldman
Saturday 0800 - 1300 Surface 1 Carole Lehoux Duval
Saturday 0800 - 1300 Surface 2 Jacques Duval
Saturday 0800 - 1300 Surface 3 Jonathon Haas

==============================================================================================

Verify Depths at new Std. Install

6/30/2015
Verify depths at concrete blocks for moorings that are getting the new standard for 100' grid

Day and TimeTaskSupport Personnel
Tuesday 1700 - 1900 Surface 1 John Rivolta
Tuesday 1700 - 1900 Surface 2 Jonathon Haas
Tuesday 1700 - 1900 Surface 3 Zoltan Sachs
Tuesday 1700 - 1900 Surface 4 Dave Jillson

==============================================================================================

Surface maintenance

7/4/2015
Add teflon discs and other work as required.

Day and TimeTaskSupport Personnel
Saturday 0700 - 1000 Surface 1 Jacques Duval
Saturday 0700 - 1000 Surface 2 Carole Lehoux Duval
Saturday 0700 - 1000 Surface 3 Robert Rochon

==============================================================================================

Surface inspections

7/11/2015
Document missing teflon discs and other surface work to be done on Monday & Tuesday

Day and TimeTaskSupport Personnel
Saturday 0700 - 1000 Surface 1 Jonathan Brooks
Saturday 0700 - 1000 Surface 2 Bruno St. Pierre
Saturday 0700 - 1000 Surface 3 Scott Jeter

==============================================================================================

Surface maintenance POSTPONED ! ! ! ! ! ! !

7/14/2015
Add/replace teflon discs and any other surface work required The mooring puller engine is down

Day and TimeTaskSupport Personnel
Tuesday 1700 - 1900 Surface 1 Kenneth Britting
Tuesday 1700 - 1900 Surface 2 Bruce Nelson
Tuesday 1700 - 1900 Surface 3 John Rivolta
Tuesday 1700 - 1900 Surface 4 Volunteer Needed

==============================================================================================

Verify replacement lines POSTPONED

7/19/2015
Will be rescheduled after all the inspections are completed.

Day and TimeTaskSupport Personnel
Sunday 0800 -1000 Diver 1 Zoltan Sachs
Sunday 0800 -1000 Surface 1 David Jillson
Sunday 0800 -1000 Surface 2 Volunteer Needed
Sunday 0800 -1000 Surface 3 Jonathon Haas

==============================================================================================

Verify Water Depths

8/1/2015
Verify water depths at moorings that need lines replaced and moorings scheduled for upgrade in the 100 grid

Day and TimeTaskSupport Personnel
Saturday 0700 - 0915 Surface 4 Jonathon Haas
Saturday 0700 - 0915 Surface 1 Benoit Bourgoin
Saturday 0700 - 0915 Surface 2 Stewart Boyd
Saturday 0700 - 0915 Surface 3 Richard Wright

==============================================================================================

Deposit stainless steel donuts in members boats

8/9/2015
This date is totally open and will actually probably be done in June or July so if you are interested, let Jonathon know please. This should take only a couple of hours to do all of the donuts. Thank you!

Day and TimeTaskSupport Personnel
Sunday 1300 - 1500 Surface 1 Bruce Nelson
Sunday 1300 - 1500 Surface 2 Alison Pechenick
Sunday 1300 - 1500 Surface 3 Jonathon Haas

==============================================================================================

Continue underwater maintenance

8/22/2015
Maintenance as required, relocate orange trawl floats

Day and TimeTaskSupport Personnel
Saturday 0700 - 1200 Diver 1 Kenneth Britting
Saturday 0700 - 1200 Diver 2 Perry Condon
Saturday 0700 - 1200 Surface 1 Jonathan Brooks
Saturday 0700 - 1200 Surface 2 Richard Wagner
Saturday 0700 - 1200 Surface 3 Robert Chase

==============================================================================================

Conclude underwater maintenance

8/29/2015
Maintenance as required, relocate orange trawl floats

Day and TimeTaskSupport Personnel
Saturday 0700 - 1200 Diver 1 Perry Condon
Saturday 0700 - 1200 Diver 2 Lennart Lundblad
Saturday 0700 - 1200 Surface 1 Richard Wright
Saturday 0700 - 1200 Surface 2 Bill Whalen
Saturday 0700 - 1200 Surface 3 David Jillson

==============================================================================================

Begin install of new standard for 100 grid POSTPONED

9/5/2015
Postponed one week due to lack of mooring lines ready for installation

Day and TimeTaskSupport Personnel
Saturday 0700 - 1200 Diver 1 Gerald Couture
Saturday 0700 - 1200 Diver 2 Volunteer Needed
Saturday 0700 - 1200 Surface 1 Denis Lambert
Saturday 0700 - 1200 Surface 2 Kevin Kuzio
Saturday 0700 - 1200 Surface 3 Richard Wright

==============================================================================================

Begin install of new standard for 100 grid POSTPONED

9/12/2015
Begin install of upgrade in 100 grid and conclude relocation of orange trawl floats

Day and TimeTaskSupport Personnel
Saturday 0700 - 1200 Diver 1 Volunteer Needed
Saturday 0700 - 1200 Diver 2 Volunteer Needed
Saturday 0700 - 1200 Surface 1 John Rivolta
Saturday 0700 - 1200 Surface 2 Stuart Pratt
Saturday 0700 - 1200 Surface 3 Denis Lambert

==============================================================================================

Reballasting hazeletts

10/31/2015
Weekday or Saturday. Time is negotiable. This session will be wind dependent so the notice may be short or date may change.

Day and TimeTaskSupport Personnel
Surface 1 Bruce Nelson
Surface 2 Alison Pechenick
Surface 3 Jonathon Haas

==============================================================================================

this is atest

11/15/2015

Day and TimeTaskSupport Personnel
Volunteer Needed

==============================================================================================

Mooring Field Closing (Final Sweep)

11/22/2015
This day will involve a final sweep of the mooring field and removing any mooring lines left on by members, adding donuts where required, removing the mooring puller from the water and decommissioning. End of the day will actually be determined by the amount of extra work we need to do. It may be determined that two shifts are required. Notice will be posted as soon as possible.

Day and TimeTaskSupport Personnel
Sunday 1300 - 1600 Surface 1 Ken Nitchie
Sunday 1300 - 1600 Surface 2 Volunteer Needed
Sunday 1300 - 1600 Surface 3 Alison Pechenick
Sunday 1300 - 1600 Surface 4 Bob Huskisson
Sunday 1300 - 1600 Surface 5 Jonathan Brooks
Sunday 1300 -1600 Surface 6 Jonathon Haas

==============================================================================================

Testing Session

1/26/2016
This is a test about sessions

Day and TimeTaskSupport Personnel
Saturday 1000-1100 Shoveling Snow Volunteer Needed

==============================================================================================

Dog Breath is alive

5/12/2016
a group of people appointed for a specific function, typically consisting of members of a larger group.

Day and TimeTaskSupport Personnel
Saturday 1000-1100 Underwater breathing Mark Gardner
Saturday 1000-1100 Building a Doghouse Mark Gardner
Saturday 1000-1100 Building a Doghouse Volunteer Needed
Saturday 1000-1100 Building a Doghouse Volunteer Needed
Saturday 1000-1100 Building a Doghouse Volunteer Needed
test test Mark Gardner


Any questions or suggestions, contact Webmaster@mbbc-vt.org              MBBC Weather
Facebook

662 West Lakeshore Drive Colchester, VT         Lat/Long: 44.550061N/73.227274W
Mailing: PO Box 402, Colchester VT 05446
 
We Support The
Malletts Bay Sailing Education Foundation